Report for January 2017
- Report Date
- January 2018
Achievements in the last period
- Phase 2 planning (scope, milestones and budget).
- Requirements for Phase 2 agreed and JIRAs assigned for design work
- Start of phase 2 design and build work.
Issues
-
none to note
Next steps
- Complete design for Phase 2
- Complete SLA
- Complete build
| 07-Feb-2018 | Phase 2 - Analysis and Design Sign Off |
| 06-Mar-2018 | Phase 2 - Build Sign Off |
| 16-Mar-2018 | Phase 2 - UAT Sign Off |
| 29-Mar-2018 | Phase 2 - Deployment to LIVE |
| 13-Apr-2018 | Phase 2 - Deployment Sign Off |
| 27-Apr-2018 | Project Closure |
- Approved budget
- 130.0 days
- Activity this month
- 4.5 days
- Activity this year
- 68.0 days
- Activity to date
- 103.0 days
- Estimate to complete current year
- 24.0 days
- Estimate to complete future years
- 0.0 days