Report for April 2018
- Report Date
- April 2018
Achievements in the last period
- Completion of build and pre-deployment checks
- UAT sign off
- Deployment to LIVE for Phase 2 JIRAs
- Complete SLA
- Phase 3 requirements, budget and timeline agreed
Issues
-
none
Next steps
- Complete graphic design for Phase 3
- Refresh TEST ahead of data upload of Sql data
- test upload to TEST of data upload process
- Build Phase 3 enhancements
- start UAT for Phase 3 enhancements
RAG - AMBER - CHANGE: Additional Phase 3 requirements requested by Sponsor to complete project.
- Approved budget
- 130.0 days
- Activity this month
- 3.5 days
- Activity this year
- 86.5 days
- Activity to date
- 122.0 days
- Estimate to complete current year
- 28.5 days
- Estimate to complete future years
- 0.0 days