Report for May 2018
- Report Date
- May 2018
Achievements in the last period
- Phase 3 graphic design completed and signed off
- TEST and STAGING refreshed
- Sql upload completed and signed off in LIVE
- Phase 3 build estimate provided
- Agreement reached between ESPA and Apps over developer costs
Issues
-
none
Next steps
- Build Phase 3 enhancements
- start UAT for Phase 3 enhancements
- deployment to LIVE for Phase 3
RAG - AMBER - CHANGE: Additional Phase 3 requirements agreed extended the milestones and budget.
- Approved budget
- 154.0 days
- Activity this month
- 4.0 days
- Activity this year
- 90.0 days
- Activity to date
- 125.0 days
- Estimate to complete current year
- 20.0 days
- Estimate to complete future years
- 0.0 days