Report for June 2018
- Report Date
- June 2018
Achievements in the last period
- Phase 3 build complete
- Phase 3 UAT complete and signed off
- Preparations made for Phase 3 deployment
Issues
-
none
Next steps
- deployment to LIVE for Phase 3
- Project closure
RAG - GREEN - no issues and project remains within budget and tolerances for milestones
- Approved budget
- 145.0 days
- Activity this month
- 9.0 days
- Activity this year
- 102.0 days
- Activity to date
- 137.0 days
- Estimate to complete current year
- 8.0 days
- Estimate to complete future years
- 0.0 days