Report for July 2018
- Report Date
- July 2018
Achievements in the last period
- Phase 3 deployment to LIVE complete
- Minor post deployment updates built, tested and deployed to LIVE
- Project closure document drafted for comment
- Agreement to proceed to formal closure
Issues
-
none
Next steps
- Project closure
RAG - BLUE - no issues and project closure agreed
- Approved budget
- 145.0 days
- Activity this month
- 6.0 days
- Activity this year
- 108.0 days
- Activity to date
- 140.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days