Report for May 2017
- Report Date
- May 2017
Achievements in the last period
- UX workshops delivered.
- Contract resource identified and recruited to support analysis and discovery.
- Back-end discovery and analysis begun.
- Project brief (planning) re-approved.
Issues
-
None
Next steps
- Project brief planning milestone completed.
- Analysis & discovery completed.
- Transformation of UX and investigation products into product backlogs completed.
Milestones
| Target Date |
Previous Date | Title | Stage | Complete | |
|---|---|---|---|---|---|
| 21-Apr-2017 | No date available | Brief sign-off | Initiate | Yes | |
| 09-Jun-2017 | 21-Apr-2017 | Planning sign-off | Plan | Yes | |
| 04-Jul-2017 | 25-May-2017 | Discovery end: UX Requirements and back-end analysis defined & signed off | Analyse | No | |
| 04-Jul-2017 | 25-May-2017 | Back-end design sign-off | Analyse | No | |
| 20-Sep-2017 | 24-Jul-2017 | Development Build Sign-off | Build | No | |
| 21-Sep-2017 | 25-Jul-2017 | Install in Test | Integrate | No | |
| 25-Sep-2017 | 27-Jul-2017 | Integration / system test sign-off | Integrate | No | |
| 02-Oct-2017 | 04-Aug-2017 | User Acceptance sign-off | Accept | No | |
| 03-Oct-2017 | 07-Aug-2017 | Deploy to live | Deliver | No | |
| 16-Oct-2017 | 08-Aug-2017 | Deployment / handover to support sign-off | Deliver | No | |
| 16-Oct-2017 | 22-Aug-2017 | Post-implementation support sign-off | Deliver | No | |
| 27-Oct-2017 | 29-Aug-207 | Project Closure | Close | No |
- Approved budget
- 154.0 days
- Activity this month
- 7.7 days
- Activity this year
- 14.8 days
- Activity to date
- 14.8 days
- Estimate to complete current year
- 26.2 days
- Estimate to complete future years
- 100.8 days
