Report for June 2017
- Report Date
- June 2017
Achievements in the last period
- UX use case and persona elaboration progressed.
- Access to SQL Server db back-end agreed.
- Back-end databases & feeds discovery - recommendations made to customer and agreed.
- Access to Drupal instances and scripts requested.
- Technical Architecture Document drafted - review and expansion ongoing.
Issues
-
Issue - Completion of Discovery/Analysis milestones delayed due to inability to access EDINA Drupal instances and scripts. A Drupal archive has now been made available (17/07/17). The Thompson/Reuters feed scripts and objects are outstanding - a timescale for receipt has been requested (17/07/17).
Next steps
- Gain access to EDINA Drupal instance and scripts.
- Carry out Drupal/SQL Server gap analysis.
- Complete use case and persona elaboration.
- Complete Technical Architecture Document.
- Transform UX and investigation products into product backlog.
- Complete Delivery / Analysis milestones.
- Replan delivery of project on that basis.
Milestones
| Target Date |
Previous Date | Title | Stage | Complete | |
|---|---|---|---|---|---|
| 21-Apr-2017 | No date available | Brief sign-off | Initiate | Yes | |
| 09-Jun-2017 | 21-Apr-2017 | Planning sign-off | Plan | Yes | |
| 04-Jul-2017 | 25-May-2017 | Discovery end: UX Requirements and back-end analysis defined & signed off | Analyse | No | |
| 04-Jul-2017 | 25-May-2017 | Back-end design sign-off | Analyse | No | |
| 20-Sep-2017 | 24-Jul-2017 | Development Build Sign-off | Build | No | |
| 21-Sep-2017 | 25-Jul-2017 | Install in Test | Integrate | No | |
| 25-Sep-2017 | 27-Jul-2017 | Integration / system test sign-off | Integrate | No | |
| 02-Oct-2017 | 04-Aug-2017 | User Acceptance sign-off | Accept | No | |
| 03-Oct-2017 | 07-Aug-2017 | Deploy to live | Deliver | No | |
| 16-Oct-2017 | 08-Aug-2017 | Deployment / handover to support sign-off | Deliver | No | |
| 16-Oct-2017 | 22-Aug-2017 | Post-implementation support sign-off | Deliver | No | |
| 27-Oct-2017 | 29-Aug-207 | Project Closure | Close | No |
- Approved budget
- 154.0 days
- Activity this month
- 7.7 days
- Activity this year
- 22.9 days
- Activity to date
- 22.8 days
- Estimate to complete current year
- 19.5 days
- Estimate to complete future years
- 100.7 days