Report for December 2017
- Report Date
- December 2017
Achievements in the last period
- Resolution of post deployment issues
- Font size amended following user feedback
- Deployment sign off for Phase 1
Issues
-
Planning for Phase 2 has been delayed to January due to conflicting diaries. It was agreed that although this is a risk to project momentum that this additional time will give ESPA and site users a longer opportunity to review the site and reflect on what should be included in Phase 2. The planning meeting has been scheduled for 15th January.
Next steps
- Phase 2 planning (scope, milestones and budget).
- Complete SLA
- Start phase 2 build work.
Milestones
| Target Date |
Title | Complete |
|---|---|---|
| 22-Nov-2017 | Post-implementation support sign-off | No |
| 12-Jan-2018 | Phase 2 Planning | No |
| 30-Mar-2018 | Project Closure | No |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days