W/C 9th April

  • Additional early supplier engagement conducted;
  • First draft of supplier analysis completed;
  • Project team meeting held with revised project plan agreed;
  • Business requirements meeting set up to review Estates requirements in line with project scope;
  • Time spent with Estates team to review WebCentral PPM module.

Project Info

Project
Fire Management System
Code
CSG013
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Lee-Ann Simpson
Project Sponsor
ALASTAIR Reid
Current Stage
Close
Status
Closed
Start Date
06-Nov-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Jul-2018
Overall Priority
Normal