w/c 29th January 2018

  • Weekly project team meeting
    • confirmed revised project timescales to extend the following phases within the Business Analysis
      • Map Existing Processes by 2 weeks
      • Requirements Gathering by a further week
      • Web Central Gap Analysis as a result of the above
      • No changes to previous defined project milestones
  • Business Analysis
    • Review of Map Existing Processes undertaken for Wednesday 31st January and Friday 2nd February
  • Project Team Administration
    • Project Risk Register reviewed
    • Project Team meetings scheduled to the end of May

Project Info

Project
Fire Management System
Code
CSG013
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Lee-Ann Simpson
Project Sponsor
ALASTAIR Reid
Current Stage
Close
Status
Closed
Start Date
06-Nov-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Jul-2018
Overall Priority
Normal