Report for February 2018
- Report Date
- February 2018
Achievements
- Business Analysis
- The current 'As-Is' processes have been documented and signed-off
- The business requirements have been documented and circulated for approval
- Continued search undertaken to identify potential market supplied solutions
- Project re-planned to incorporate additional time for business requirements
Issues
- Additional time required to complete the business analysis to incorporate the activities noted below, it is not anticipated that the overall project timelines will be impacted at this time
- additional workshop to clarify all business requirements from the Fire Safety team
- additional workshop to review business requirements with selected business partners
Next Steps
- Consultation workshop scheduled with selected business partners to review business requirements
- Sign-off business requirements
- Demonstration of potential solution arranged for 3rd April
- Commence gap analysis review with regards to
- existing Archibus modules
- potential market supplied solutions
- Approved budget
- 50.0 days
- Activity this month
- 5.7 days
- Activity this year
- 26.2 days
- Activity to date
- 26.2 days
- Estimate to complete current year
- 27.4 days
- Estimate to complete future years
- 0.0 days