Report for April 2018

Report Date
April 2018

Achievements

  • Project plan revised to include delay due to Archibus demo which took place on the 24th April.
  • Requirements gathering workshop undertaken with Estates to determine joint requirements for the Archibus demo.
  • Additional market supplied solutions identified and reviewed as part of the Early Market engagement.

Issues 

  • In March, the business lead has expressed concerns regarding a potential delay to reviewing the Archibus WebCentral modules and the impact of the project being extended by four week.  This was reviewed by the project team and the project plan was updated to reflect the delay.
  • Due to A/L commitments of the Fire Safety Team during April, a subsequent Webinar has been requested by Archibus to allow a bespoke demonstration to be conducted.

Next Steps 

  • Webinar dates to be confirmed for the Fire Safety demonstration.
  • Complete gap analysis review once Fire Safety demo has been undertaken with regards to: 
    • Existing Archibus modules
    • Potential market supplied solutions  
  • Continue business report.
  • ARUP supplier demonstration to be conducted by Fire Safety Team.
  • Review requirements with Fire Safety team and project sponsor to understand if they are all still in scope for this project or not.
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Change: Project delivery has been delayed by 4 weeks due to the scheduling of selected Archibus WebCentral modules demonstration by the supplier and subsequent Webinar for the Fire Safety Team to account for A/L during the initial demonstration. This has been approved by the project team and sponsor
Change Status
Activity
Approved budget
50.0 days
Activity this month
8.9 days
Activity this year
38.6 days
Activity to date
38.6 days
Estimate to complete current year
15.2 days
Estimate to complete future years
0.0 days

Project Info

Project
Fire Management System
Code
CSG013
Programme
CSG Portfolio Projects (OTHCSG)
Management Office
ISG PMO
Project Manager
Lee-Ann Simpson
Project Sponsor
ALASTAIR Reid
Current Stage
Close
Status
Closed
Start Date
06-Nov-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Jul-2018
Overall Priority
Normal