Report for May 2018
- Report Date
- May 2018
Achievements
- Archibus webinar held on 18th May for the Fire Safety demonstration.
- Completed gap analysis review once Fire Safety demo has been undertaken with regards to:
- Existing Archibus modules
- Potential market supplied solutions
- Continued business report.
- ARUP supplier demonstration for the Fire Safety Team held on 10th May.
- Reviewed requirements with Fire Safety team and determined they were all still in scope.
- Last minute demonstration held with FCS to review their product and include in the business analysis.
Issues
- Last minute demonstration of 3rd party provider requested by business lead has delayed the finalised business analysis and may push the project over budget.
Next Steps
- Complete business analysis to include FCS demonstration.
- Finalise business analysis and prepare recommendations.
- Provide recommendations to the project team.
- Create closure report.
- Close project.
- Approved budget
- 50.0 days
- Activity this month
- 5.6 days
- Activity this year
- 44.4 days
- Activity to date
- 44.4 days
- Estimate to complete current year
- 10.5 days
- Estimate to complete future years
- 0.0 days