Report for September 2020

Report Date
September 2020

Achievements in this period

  • Microsoft Stream was enabled
  • Project closure report and process completed

Issues

  • None

Next Steps

  • None
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Online and Digital Events Service
Code
DTI053
Programme
Digital Transformation - Online and Digital Events Programme (DTIODE)
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Gavin McLachlan
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
29-May-2020
Planning Date
05-Jun-2020
Delivery Date
04-Sep-2020
Close Date
18-Sep-2020
Overall Priority
Highest
Category
Discretionary