Project Status Reports

Title Report Date Time Cost Scope Overall Change
Current Status July 2013 GREEN GREEN GREEN BLUE
Report for June June 2013 GREEN
Report for May May 2013 GREEN
Report for April April 2013 GREEN
Report for March March 2013 GREEN GREEN GREEN GREEN
Report for February February 2013 GREEN
Report for January January 2013 AMBER
Report for November November 2012 GREEN
Report for October 2012 October 2012 GREEN
Report for September 2012 September 2012 AMBER
Report for August 2012 August 2012 AMBER
Project in suspension no progress to report. July 2012 AMBER