The key objectives of the FY2018-19 Disaster Recovery project are to -
-
Review and update the current inventory of ITI Enterprise Services (ENT) Disaster Recovery documentation
- Confirm services ranking as high, medium and low
- Update existing documentation for critical systems
- Load balancers
- TSM
- Veeam
- Virtual hosting
- SAN
- Mail relays
- Central Authorisation
- Active Directory
- Shibboleth
- EASE
- ADFS (added to scope)
- Plan and run DR tests for selective ENT systems - Active Directory, EASE
The expectation is that the work will be completed before the September 2019 change freeze.
Additional project documentation can be found on the project SharePoint site and works is tracked using a Jira Kanban dashboard.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
January 2020 | BLUE | 60.0 days | 71.0 days | 0.0 |