Deployment
-
Deployment Strategy - Bamboo used to deploy production code on Tuesday April 24th at 12pm. This task to be done by IS Apps Management. Developer will be available also.
-
Dependencies - Checked service alerts and no dependencies occurring on this date and time that will affect this project.
-
Communication - Health and Safety to communicate to users that application will be unavailable and when available again,
-
Deployment Checklists
Application checklist
|
Component |
Success Criteria |
Project Stage Required (Agile) |
OK (Y/N) | Reviewed by (date) | Outstanding Actions (Who) |
|---|---|---|---|---|---|
|
Implementation Plan (including Rollback plan) |
Implementation plan has been followed to deploy to Test and updated in case of issues found Rollback plan has been documented. Production Branch in Bamboo can be deployed to overwrite project changes in the event of issues occurring. |
DSOR (Release 1-n) |
Y |
John Chan 13/04/18 |
|
|
Implementation Risk Assessment |
A risk assessment has been undertaken for the Implementation Plan and selected deployment dates. Approved by GoCab |
ASOR (Release 1-n) |
Y |
John Chan 13/04/18 |
|
|
TAD/Operational Document |
Documentation complete Action: The Document must be copied to the Wiki No changes to TAD |
ASOR (Release 1-n) |
Y |
John Chan 13/04/18 |
|
| Update End Of Life (EOL) spreadsheet |
Review EOL spreasheet to ensure new versions and servers are updated or added to this list. Sharedpoint with USG, CSG and ISG EOL spreadsheet https://uoe.sharepoint.com/sites/TechnologyEndOfLife2018 Current EOL technology register No change |
ASOR (Final Release / Handover) | Y |
John Chan 13/04/18 |
|
|
System Design Specification (SDS) |
Document complete and accurate.
Action: The Document must be copied to the Wiki |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/18 |
|
|
System Description Document |
Document complete, accurate and it has been reviewed by Application Management
Action: The Document must be copied to the Wiki version 1.9 uploaded |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/18 |
|
|
Scalability/Load Testing |
Adequate load testing has taken place. The results have been recorded and analysed to ensure that the application will cope with the anticipated load. No change to number of users. |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/18 |
|
|
Performance |
The application has been tested against stated performance criteria. Performance has been assured by user and support staff testing. No issues raised with the performance of running the reports/application during UAT.
|
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/18 |
|
|
Source Code available in GIT
|
Source code has been secured in GIT and Production branch is up-to-date Action: ensure Production Branch created Where code is provided by a third party (e.g. supplier) it has been established who is responsible to maintain source code Source code not in GIT but still in SVN.
|
DSOR (Final Release / Handover) |
N |
John Chan 13/04/18 |
Jchan to check Production Branch. Latest one is prod_1.13.x |
|
Configuration Management Database |
The relevant details regarding new or changed infrastructure components have been added to the CMDB in unidesk To be reviewed as there are still issues. Ji ra raised. |
ASOR (Release 1-n) |
N |
John Chan 13/04/18 |
|
|
Change Control(s) |
A Change & Release record has been created in Unidesk for the LIVE implementation request and notified to GoCAB if necessary Action: Record Unidesk number C1803-052 |
ASOR / (Release 1-n) |
Y |
John Chan 13/04/18 |
|
|
Test Log Review |
A review of the test log (JIRA) has taken place to ensure all required actions have been completed. If this is not the case, then confirmation on criticality of outstanding issues and action plan for resolution is required. Must have Jiras have been completed. There are still other outstanding Jiras. To be reviewed by projects team. |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/18 |
|
|
Application Management Handover |
Handover to Application Management and Development team is completed or arranged. Action: record handover dates JC and GP had handover on 12/04/18 at 10am-11am |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/18 |
|
|
Support Accounts |
Read access accounts or update current read access accounts have been set up for support staff(requires business owner approval) No change |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/18 |
|
|
Password Manager (PMP) |
InfoKeep has been updated with all relevant account details including external supplier accounts No change. |
ASOR (Release 1-n) |
Y |
John Chan 13/04/18 |
|
|
Environment comparison |
Database comparison between TEST and LIVE (might be required before and after go-live) Not required as database object changes being done via Bamboo. |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/2018 |
|
|
Client requirements |
Does the application have specific client requirements, such as JVM/JRE versions, JInitiator etc If so have these requirements been raised with Desktop services Wiki pages to be updated: [1] https://www.wiki.ed.ac.uk/display/insite/Corporate+applications+with+client+based+requirements [2] https://www.wiki.ed.ac.uk/display/insite/Client+side+requirements+for+co... |
ASOR (Release 1-n) |
Y |
John Chan 13/04/2018 |
|
|
Technologies |
Is there any new software or technologies involved? (Y/N) If yes state any additional actions taken to ensure adequate handover to the production support team |
ASOR (Release 1-n) |
N |
John Chan 13/04/2018 |
|
|
Access outside University |
By default all web based applications are accessible outside University without use of VPN etc Wiki list If not accessible from outside University this needs to be approved by Production Management. |
ASOR (Release 1-n) |
Y |
John Chan 13/04/2018 |
|
|
Vendor Access Required |
Does vendor require db/app access (Y/N) If yes, ensure access details are in TAD |
ASOR (Final Release / Handover) |
N |
John Chan 13/04/2018 |
|
|
Certificates |
All changes to certificates or new certificates for this service have to be added to the certificate master list. The certificate master list is being managed by Applications Management This includes TEST and LIVE certificates and records type of certificate and expiry dates. no change |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/2018 |
|
|
Deployment Date(s) |
Agreed date has been confirmed that allows adequate time for completion of Acceptance Sign Off Review. See deployment strategy |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/2018 |
|
|
Deployment Resources |
IS and business area resources required for deployment, including those needed for post implementation checking and sign off have been secured. |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/2018 |
|
|
Deployment Ownership |
Responsibilities for managing the go-live, including: comms with service owner and end users, ensuring go live timescales are met, managing issues arising and managing comms between all teams involved in go live. |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/2018 |
|
|
Service Announcement(s) |
A Service announcement has been raised with the agreed deployment date on the alert system:
http://reports.is.ed.ac.uk/alerts/
Service announcements should be raised by Project Manager 10 days before go live, but no later than 4 days. http://reports.is.ed.ac.uk/alerts/index.cfm?fuseaction=view_alert&alert_id=7431
|
ASOR (Release 1-n) |
Y |
John Chan 13/04/2018 |
|
|
Reporting and Analytics |
New BI Universes or substantial changes to Universes/report offerings need to be documented in the Information Portal managed by GaSP. https://www.wiki.ed.ac.uk/display/IP/Information+Portal+Home No change to the RETAIN universe |
ASOR (Release 1-n) |
Y |
John Chan 13/04/2018 |
|
| 24x7 monitoring setup |
Consider if a new application needs to be added to 24x7 monitoring tool Not added to 24x7 this time. |
ASOR (Release 1-n) | Y |
John Chan 13/04/2018 |
Infrastructure checklist
|
Component |
Success Criteria |
Project Stage Required (Agile) |
OK (Y/N) | Reviewed by (date) | Outdstanding Actions (Who) | ||
|---|---|---|---|---|---|---|---|
|
Technical Architecture/Operational Document(TAD) |
Documentation complete and accurately reflects the environment subjected to UAT. no change
|
ASOR (Release 1-n) |
Y |
John Chan 13/04/2018 |
|||
|
Security |
All security requirements, e.g. SSL encryption, IP based restrictions firewall requirements have been specified, tested and implemented in LIVE no change |
ASOR (Release 1-n) |
Y |
John Chan 13/04/2018 |
|||
|
User Accounts |
no change | Y |
John Chan 13/04/2018 |
||||
|
Patching |
Ensure that all applications have an agreed patching schedule and this schedule is agreed with service owners. Different technologies have different patching strategies: Action update wiki: Windows, Linux no change |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/2018 |
|||
|
Start/Stop scripts |
Are Server Start-up/Shutdown scripts in place? Including start-up procedure documented, enabled and tested no change |
ASOR (Release 1-n) |
Y |
John Chan 13/04/2018 |
|||
|
Ports |
Port allocation file been updated:
https://www.wiki.ed.ac.uk/display/insite/Port+Allocation+on+Unix+Servers no change |
ASOR (Release 1-n) |
Y |
John Chan 13/04/2018 |
|||
|
Backup and Recovery |
All backups as noted in the TAD need to be confirmed operational.
A test recovery of user data needs to be done to validate the integrity of the recovery mechanism and process. no change |
ASOR (Release 1-n) |
Y |
John Chan 13/04/2018 |
|||
|
DR Copy |
DR copy to SECONDARY DB configured and tested (unless existing database which is already setup). no change |
ASOR/Release1 |
Y |
John Chan 13/04/2018 |
|||
|
Logs |
For all logs the following is in place:
no change |
ASOR (Release 1-n) |
Y |
John Chan 13/04/2018 |
|||
| Decommission |
If project deploying new server make sure old servers are being decommission including removing passwords from PMP and patching restart Wiki no change |
ASOR (Release n) | Y |
John Chan 13/04/2018 |
|||
| Servers are being scanned by Nessus |
Check that new and existing servers are being scan by Nessus no change |
ASOR (Final Release / Handover) | Y |
John Chan 13/04/2018 |
|||
|
Technology Management Handover |
Handover to Technology Management and Development Technology is completed or arranged. Action: record handover dates No handover required as only code changes. |
ASOR (Final Release / Handover) |
Y |
John Chan 13/04/2018 |
Support checklist
|
Component |
Success Criteria |
Project Stage Required (Agile) |
OK (Y/N) | Reviewed by (date) | Outdstanding Actions (Who) |
|---|---|---|---|---|---|
|
Support Agreement (including any charging arrangements) |
A support agreement OLA is in place for any new applications – including any hosting or support charges. Where external suppliers are involved an SLA should be in place as well.
Action: SLA moved to wiki:
https://www.wiki.ed.ac.uk/display/insite/SLA+repository+-+Applications+Management |
ASOR (Final Release / Handover) |
Y |
Jchan 13/04/2018 |
|
| AppCatalogue updated |
For new and existing application update the Appcatalogue |
ASOR (Final Release / Handover) | Y |
Jchan 13/04/2018 |
|
|
Time Recording Code |
A Time Recording code for the application, if required, has been confirmed and set up (in ASTA) Action: Does application require a separate entry for business area in ASTA |
ASOR (Final Release / Handover) |
Y |
Jchan 13/04/2018 |
|
|
Disaster Recovery and Business Continuity |
Appropriate DR/BC provision is in place and has been fully tested. Application DR/BC details have been transferred to the DR Portfolio and DR level (1, 2 or 3) has been agreed |
ASOR (Release 1-n) |
Y |
Jchan 13/04/2018 |
|
|
Test Environment |
An adequate TEST environment has been established for the application which may be used by support to test future changes prior to releasing these in the LIVE environment. |
ASOR (Release 1-n) |
Y |
Jchan 13/04/2018 |
|
|
Hardware and Software Licensing |
All required licensing is in place including maintenance/support arrangements with external suppliers. no change |
ASOR (Final Release / Handover) |
Y |
Jchan 13/04/2018 |
|
|
Browser Compatibility |
Browser compatibility has been tested and compatibility information updated See for details no change |
ASOR (Final Release / Handover) |
Y |
Jchan 13/04/2018 |
|
|
Portal Compatibility |
Portal compatibility, where required, has been confirmed the Portals Service Owner. no portal |
ASOR (Final Release / Handover) |
Y |
Jchan 13/04/2018 |
|
|
Help Desk |
The new application is recognised with the UniDesk (A business contact queue is defined where initial calls are raised with) no change |
ASOR (Final Release / Handover) |
Y |
Jchan 13/04/2018 |
|
|
User Guide Documentation |
Appropriate documentation has been produced for users of the new application. to be done by H&S |
ASOR (Final Release / Handover) |
Y |
Jchan 13/04/2018 |
|
|
Training Material |
Training material, if required, has been produced and is of an appropriate standard. to be done by H&S |
ASOR (Final Release / Handover) |
Y |
Jchan 13/04/2018 |
|
|
Demonstration or Walkthrough |
Demonstration or walkthrough of the new application has taken place for other stakeholder. not required |
ASOR (Final Release / Handover) |
Y |
Jchan 13/04/2018 |
|
|
Web Sites and Other Document Sources |
External and internal web sites have been reviewed to ensure that all application references are present, correct and up to date. RETAIN wiki updated accordingly |
ASOR (Final Release / Handover) |
Y |
Jchan 13/04/2018 |