Report For February 2018

Report Date
February 2018

Achievements this period

Production environment has been completed.  Integration testing has revealed access and permission configuration issues requiring further testing to ensure appropriate segregation of duties. 

The original business requirements have been misleading.  Access to the data sources SPQS and Inventory was to existing BI Universes, not the database tables.

Significant additional work and training on the database structures will be required to enable meaningful connections to the data sources and dashboards. 

The impact of this delay means closure will occur three weeks later than planned. 

 

Issues

None at this time.

 

Next Steps

Complete security and access tasks and close project.

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
46.0 days
Activity this month
12.4 days
Activity this year
29.9 days
Activity to date
29.9 days
Estimate to complete current year
16.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Power BI Gateway Service
Code
HSS019
Programme
Z.Digital Transformation - BI Tools (DTIP08) - CLOSED
Management Office
ISG PMO
Project Manager
Geoff Cropley
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
18-Sep-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
18-May-2018
Overall Priority
Normal
Category
Discretionary

Documentation