Undertook quality and price evaluation including scoring written responses, scoring demo and scoring commercials (pricing)
Ran supplier demos / scenario evaluation session
Ran consensus meeting
Issues
The evaluation has taken a couple of weeks longer than expected, so the timeline for awarding a contract is also set to move back a couple of weeks. Efforts are being made to ensure that the award of the contract can be made in time for the college to use funding from 17/18 for the first year payment to the successful bidder. As a result, the RAG for Time has been marked as AMBER this month.