Report for November 2022

Report Date
November 2022

Achievements this period

  • Project Initiation approved

Issues

  • None

Next Steps

  • Development of project brief

Milestones

Milestone Due Date
Planning Complete 14-Jan-2023
Delivery Complete 14-Jul-2023
Project Closure 28-Jul-2023
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
140.0 days
Activity this month
5.1 days
Activity this year
6.5 days
Activity to date
6.5 days
Estimate to complete current year
132.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ISG Services for EFI Launch - Phase 1
Code
HSS041
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Rick Arnautovic
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
28-Nov-2022
Planning Date
17-Mar-2023
Delivery Date
04-Sep-2023
Close Date
15-Dec-2023
Programme Priority
1
Overall Priority
Normal
Category
Discretionary