Report for August 2023
- Report Date
- August 2023
Achievements this period
- Door cards readers received from supplier and installed
- Door access clearances provided by EFI and input
- All AV physical installs have been completed
- Network work completed in phase 1 part of building (outside of missing test results)
- ECA resilient link work underway
- Support arrangements for EFI pahse 1 drafted and out for review/agreement
Issues
- Missing ~300 test results from BBK which is preventing completion of all network work in phase 1 building
- Milestones to be formally changed
Next Steps
- Printers being installed on 5th September
- Complete ECA resilient link
- Complete snagging of doors with BBK
- Complete snagging and commissioning of AV equipment
- Assess and complete any work once missing test results received
- Complete agreement of support arrangements for phase 1
Milestones
Milestone | Due Date |
---|---|
Printers installation completed - phase 1 | 05-Sep-2023 |
ECA link completed | 08-Sep-2023 |
Door access control completed | 15-Sep-2023 |
Delivery Complete (MAJOR) | 15-Sep-2023 |
Networking for EFI opening | 15-Sep-2023 |
AV for EFI opening | 15-Sep-2023 |
Delivery review | 06-Oct-2023 |
Project Closure (MAJOR) | 27-Oct-2023 |
- Approved budget
- 140.0 days
- Activity this month
- 9.0 days
- Activity this year
- 10.6 days
- Activity to date
- 103.8 days
- Estimate to complete current year
- 14.6 days
- Estimate to complete future years
- 0.0 days