Report for September 2023
- Report Date
- September 2023
Achievements this period
- Completion of snagging and commissioing of AV equipment ready for teaching
- Completion of work on door access
- Printers installed in phase 1
- ECA resilient link completed (flip-over to be tested)
- Clarity provided from BBK on majority of missing test results
Issues
- Missing ~50 test results from BBK. BBK advised that Cat6a cables that were over 90m have not been installed. ITI have instucted AtkinsRealis (was F&G) that this work is to be completed.
- Milestones to be formally changed
- Estates have not completed key suiting for phase 1 due to delay with BBK. This has support implications as ITI CIS do not have normal 24x7 access.
- Establishing status of all WAPs still being worked on
- Problem with AVoIP has required change from multicasting to Unicast - to be worked on by LST and Network teams
Next Steps
- Assess and complete any work once missing test results received
- Test flip-over to ECA resilient link
- Complete establishing status of all WAPs in phase 1
- Obtain keys and clarity of support access for phase 1 part of building
- Complete agreement of support arrangements for phase 1
- Planning for phase 2 to begin
Milestones
Milestone | Due Date | Complete |
---|---|---|
ECA link completed | 08-Sep-2023 | No |
Delivery review | 06-Oct-2023 | No |
Project Closure (MAJOR) | 27-Oct-2023 | No |
- Approved budget
- 140.0 days
- Activity this month
- 4.9 days
- Activity this year
- 13.9 days
- Activity to date
- 107.1 days
- Estimate to complete current year
- 9.4 days
- Estimate to complete future years
- 0.0 days