Report for February 2023
- Report Date
- February 2023
Achievements this period
- Updated power and data plan received
- Desk booking requirements emailed
- Meetings with Bayes to understand their Hub set-up and to discuss lessons learned
- Sharepoint set up - to be tested and populated
- Revised F&G plan received and initial high-level plan produced for phase 1
- Demo of "fusion" teaching in EFI took place to inform requirements workshop
- Project brief drafted and out for approval
Issues
- RESOLVED: There was an issue identified with the networking in the clocktower. The sponsor has worked with ITI CIS and EFi and have reached an agreed position.
Next Steps
- Sign-off brief
- Complete requirements gathering for project and agree the baselines for all deliverables with EFI
- Populate and share the project' Sharepoint tracker
- Agree design/implementation plans for each of the objectives and deliverables
- Confirm AT and resilient ECA links completed - current milestone estimated
Milestones
Milestone | Due Date |
---|---|
AT & resilient ECA links completed | 17-Mar-2023 |
Planning Complete (MAJOR) | 17-Mar-2023 |
Requirements Gathering completed | 31-Mar-2023 |
Main Comms room complete | 31-Mar-2023 |
Door access control completed | 05-May-2023 |
Networking for EFI opening | 07-Jun-2023 |
AV for EFI opening | 28-Jul-2023 |
Delivery Complete (MAJOR) | 04-Sep-2023 |
Delivery review | 06-Oct-2023 |
Project Closure (MAJOR) | 27-Oct-2023 |
- Approved budget
- 140.0 days
- Activity this month
- 13.1 days
- Activity this year
- 37.5 days
- Activity to date
- 37.5 days
- Estimate to complete current year
- 90.6 days
- Estimate to complete future years
- 0.0 days