Report for September 2025

Report Date
September 2025

Achievements in Last Period

  • Project for this year initiated at Apps Review
  • Project brief written and draft version (link in Teams) was circulated to the project team at the fortnightly meeting 

Issues

  • No issues

Next Steps

  • Brief signoff required by Project Team and Apps Review
  • Commence with the JIRAs 

Milestones

Milestone Due Date
Brief signoff completed 17-Oct-2025   
Delivery of JIRAs in sprints completed    06-Mar-2026
Project Closure 27-Mar-2026
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Peace Agreements Database – Continuous Improvements 25/26
Code
HSS052
Programme
CAHSS Portfolio Projects
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Sanja Badanjak
Current Stage
Plan
Status
In Progress
Project Classification
Grow
Start Date
29-Aug-2025
Planning Date
26-Sep-2025
Delivery Date
06-Mar-2026
Close Date
27-Mar-2026
Overall Priority
Normal
Category
Discretionary

Documentation

Not available.