Organisation

Work/Task Breakdown

to be agreed as discussed today Resources, Skills and Costs

 

IS Apps Section Team  Estimate (Days)
     
Project Services  Project Services  14.5
Development Services Development Technology 20.0
  Enterprise Architect 5.0
   

 

Production Management  Applications Management 10.0
Directors Office Directors Office 0.5
     
  Total Days 50.0

Project Governance

 

This project will follow the standard project governance in Project Services.

Any changes to major milestones (Initiation, Planning, Delivery, Closure) will be approved by the Project Sponsor, Project Team and WIS.

Major milestones achievements and changes will be submitted to WIS for approval/noting as necessary.

Project Stakeholders

Name Business Area  Role
Alain Forrester  Service Management(Project Team Member)      Service Manager
Alex Carter  Service Management  Service Manager
Ana Heyn  Production Management  Production Manager
Andrew Hobden  Production Management  Production Manager
Graeme Wood  Development Services  Senior supplier
Heather Larnach  Production Management  Production Manager(Project Team Member)  
Mark Lang  Development Services  Senior Supplier(Project Team Member)
Martin Campbell  Enterprise Services  Technical Architect(Project Team Member)
Maurice Franceschi        IT Infrastructure Division  Programme Manager
Megan Graham  Project Services  Project Manager(Project Team Member)
Sheila Fraser  Project Services  Project Services Programme assurance
Stefan Kaempf  Production Management  Business Sponsor

Project Estimations

(Please attach/link from Estimation)

inf129_3pointestimate_12dec.xls

Project Info

Project
Wiki Database Resilience Improvement
Code
INF129
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
02-Oct-2017
Planning Date
19-Jan-2018
Delivery Date
29-Mar-2019
Close Date
12-Apr-2019
Programme Priority
5
Overall Priority
Higher
Category
Compliance