Report for February 2019

Report Date
February 2019

Achievements This Period

  • Meetings between project team to discuss direction

  • Project milestones reviewed and replanned

Issues

  • Outstanding milestones to be revised
  • Extra effort required to complete project

Next Steps

  • Complete Puppet work

  • Finalise migration of Dev Wki

  • Close project

MILESTONES

 

Stage Milestone Due Date
Deliver Phase 2 - Stage 1 Database move to VM - Delivery Complete 15-Mar-2019
Close Project Close complete 29-Mar-2019
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
CHANGE - outstanding milestones revised
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
Yes
Escalated to
Project Sponsor; Programme Manager
Change Commentary
The remaining project work has been rescheduled with the project team. Issue being reported 07/03/19.
Activity
Approved budget
90.0 days
Activity this month
3.5 days
Activity this year
68.2 days
Activity to date
89.2 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Wiki Database Resilience Improvement
Code
INF129
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
02-Oct-2017
Planning Date
19-Jan-2018
Delivery Date
29-Mar-2019
Close Date
12-Apr-2019
Programme Priority
5
Overall Priority
Higher
Category
Compliance