Report for February 2019
- Report Date
- February 2019
Achievements This Period
-
Meetings between project team to discuss direction
-
Project milestones reviewed and replanned
Issues
- Outstanding milestones to be revised
- Extra effort required to complete project
Next Steps
-
Complete Puppet work
-
Finalise migration of Dev Wki
-
Close project
MILESTONES
| Stage | Milestone | Due Date |
|---|---|---|
| Deliver | Phase 2 - Stage 1 Database move to VM - Delivery Complete | 15-Mar-2019 |
| Close | Project Close complete | 29-Mar-2019 |
- Approved budget
- 90.0 days
- Activity this month
- 3.5 days
- Activity this year
- 68.2 days
- Activity to date
- 89.2 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days