Report for March 2019

Report Date
March 2019

Achievements This Period

  • Puppet work completed

  • Migration of DEV Wiki database to new VM

Issues

  • Outstanding milestones revised
  • Extra effort required to complete project

Next Steps

  • Close project

MILESTONES

Stage Milestone Due Date
Close Project Close complete 12-Apr-2019

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
CHANGE - outstanding milestones revised; budget increased
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
Yes
Escalated to
Project Sponsor; Programme Manager
Change Commentary
The final tasks required additional effort and time to "get over the line". This has now been achieved.
Activity
Approved budget
110.0 days
Activity this month
17.3 days
Activity this year
89.9 days
Activity to date
110.9 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Wiki Database Resilience Improvement
Code
INF129
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
02-Oct-2017
Planning Date
19-Jan-2018
Delivery Date
29-Mar-2019
Close Date
12-Apr-2019
Programme Priority
5
Overall Priority
Higher
Category
Compliance