Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for December 2019 December 2019 BLUE BLUE BLUE BLUE
Report for November 2019 November 2019 GREEN GREEN GREEN GREEN
Report for October 2019 October 2019 GREEN GREEN GREEN GREEN
Report for September 2019 September 2019 GREEN GREEN GREEN GREEN
Programme Report for August 2019 August 2019 GREEN GREEN GREEN GREEN
Report for July 2019 July 2019 GREEN GREEN GREEN GREEN
Report for June 2019 June 2019 GREEN GREEN GREEN GREEN
Report for April 2019 April 2019 GREEN GREEN GREEN GREEN

Project Info

Project
IT and Library Business Service Readiness for Start of Term 2019/20
Code
ISG017
Programme
ISG Portfolio Projects (OTHISG)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Neil Bruce
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
09-Apr-2019
Planning Date
03-May-2019
Delivery Date
09-Sep-2019
Close Date
13-Dec-2019
Programme Priority
1
Overall Priority
Normal
Category
Discretionary