Project still in green status. Money to be distributed accordingly.

Report Date
March 2018

Achievements

  • Job specifications advertised
  • Job interviews arranged- three candidates for the analyst post to be interviewed on April 2-3.
  • Interview panel agreed (Scott Renton/Claire Knowles)

Issues

  • First advert (from Feb 26-March 8) received no applications for either post.
  • We had planned to shortlist on March 9, but had to readvertise
  • Industrial action
  • Second advert brought four applicants for the analyst post and none for the developer
  • We have been asking previous development interns if they'd like to apply- no availability
  • We will probably offer the development post to the most technical analyst applicant, and alter the money accordingly

Next Steps

  • Interviewing (2-3 April)
  • Appointment (hopefully 4 April)
  • Work starts (16 April)

Budget Information

  • No spend to date
  • Estimated spend £3,286
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Schema.org integration with Library and University Collections
Code
LTW006
Programme
z. ISG Learning Teaching and Web - Strategic Projects (Closed)
Management Office
ISG PMO
Project Manager
Scott Renton
Project Sponsor
Melissa Highton
Current Stage
Close
Status
Closed
Start Date
08-Jan-2018
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Aug-2018
Overall Priority
Normal

Documentation