| Deliver |
Soft launch of Archipelago platform in LIVE environment |
30-Sep-2025 |
29-Aug-2025 |
No |
| Accept |
Post-soft launch of Archipelago platform checks complete and signed off |
17-Oct-2025 |
12-Sep-2025 |
No |
| Build |
Process for migration of Managed Private Non-Goobi Material agreed and signed off |
30-Jan-2026 |
12-Jun-2026 |
No |
| Deliver |
Migration of Managed Public Non-Goobi Material into LIVE environment complete |
30-Jan-2026 |
No date available |
No |
| Accept |
Managed Public Non-Goobi Material post-migration checks complete and signed off |
13-Feb-2026 |
No date available |
No |
| Build |
Process for migration of Non-Managed Material agreed and signed off |
03-Jul-2026 |
No date available |
No |
| Build |
Process for migration of Session Papers and The Witness agreed and signed off |
10-Jul-2026 |
No date available |
No |
| Deliver |
Migration of Managed Private Non-Goobi Material into LIVE environment complete |
31-Jul-2026 |
No date available |
No |
| Deliver |
Migration of Non-Managed Material into LIVE environment complete |
31-Jul-2026 |
No date available |
No |
| Accept |
Managed Private Non-Goobi Material post-migration checks complete and signed off |
07-Aug-2026 |
No date available |
No |
| Accept |
Non-Managed Material post-migration checks complete and signed off |
07-Aug-2026 |
No date available |
No |
| Deliver |
Session Papers and The Witness migrated into LIVE environment |
14-Aug-2026 |
No date available |
No |
| Accept |
Session Papers and The Witness post-migration checks complete and signed off |
21-Aug-2026 |
No date available |
No |
| Deliver |
Full launch of Archipelago in LIVE environment (MAJOR MILESTONE) |
28-Aug-2026 |
No date available |
No |
| Accept |
Post-hard launch of Archipelago platform checks complete and signed off |
11-Sep-2026 |
No date available |
No |
| Deliver |
Final switch off of LUNA |
18-Sep-2026 |
No date available |
No |
| Close |
Project Closure (MAJOR MILESTONE) |
30-Sep-2026 |
No date available |
No |