Report forMarch 2025

Report Date
March 2025

Achievements This Period

  • Milestones agreed
  • Project brief agreed and signed off
  • GOOBI materials are being migrated (unpublished) to Archipelago

Issues

N/A

Next steps

  • Project plan to be completed
  • Project to run in tandem with LUC080
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
61.0 days
Activity this month
2.3 days
Activity this year
15.1 days
Activity to date
16.0 days
Estimate to complete current year
14.8 days
Estimate to complete future years
46.2 days

Project Info

Project
Digital Collections Migration: LUNA
Code
LUC074
Programme
Library & Collections - Digital Library BAU (LUCDL)
Management Office
ISG PMO
Project Manager
Jack Ross
Project Sponsor
Rebecca Hirsch
Current Stage
Execute
Status
In Progress
Start Date
19-Jan-2024
Planning Date
05-Mar-2025
Delivery Date
28-Aug-2026
Close Date
30-Sep-2026
Overall Priority
Normal