Project Brief
LUC078 – Library infrastructure maintenance
Project Brief
Document Sign-off
|
Name |
Role |
Date signed off |
|
Ianthe Sutherland |
Sponsor |
|
|
Scott Renton |
Technical lead |
|
|
Chris Walker |
Project Manager |
|
|
|
|
|
|
|
|
|
|
|
|
|
Working draft should be version 0.x and 1.x Draft sent for Approval/Review should be version 2.x Approved Project brief should be 3.0 Post-approval changes should be change controlled via Issue Log and Scope Change Page, and version 3.x
Background
This project is a follow on from LUC072, where the Digital Library servers were upgraded from Centos 7 to Rocky 8. This project will focus on the remaining tasks to bring the L&UC server estate up to date and includes tasks such as:
Scope
- all servers that don't need to be on a public IP range will be moved to the private VLAN
- all websites to go through the load balancer and https
- puppetisation of servers
- password manager clean up
- tracking application up to date
- ensure all servers have zabbix agent, appear in VSphere and monthly restarts
- Analytics & Monitoring per URL
Objectives and Deliverables.
This is an Agile project and as such resources will work through the backlog defined in Jira
|
Role |
Name |
|
Project Manager |
Chris Walker |
|
Service Owner |
Ianthe Sutherland |
|
Technical Lead |
Scott Renton |
|
|
|
Assumptions
- Sufficient resource is available to support the project
Constraints
- Project manager in currently contracted until 31/12/2024.
BAU Activity
Risks
- Project Manager’s contract does not get renewed beyond 31/12/2024.
Run / Grow / Transform
Run and Transform