- Report Date
- October 2025
Achievements this month
- prepare a draft one page options paper for Sponsor - done
- prepared a bid for SLT for a feasibility study to best work the way forward
Issues/Risks
Next Steps
- act on decision from SLT
- publish risk assessment and costs estimate
- close project
-
Milestones
| Deliver |
31-Oct-2025 |
| Close |
30-Nov-2025 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days