Report for Febuary 2025

Report Date
February 2025

 

Achievements this month

  • Project brief approved
  • Working sessions arranged for requirements gathering

 

Issues/Risks

  • NA

 

Next Steps

  • Complete requirements gathering

 

Milestones

To be approved

 

Delivery: 20 May 2025

Close: 27 June 2025

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
RDS Infrastructure Review
Code
LUC079
Programme
Library & Collections - Digital Library BAU (LUCDL)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Rebecca Hirsch
Current Stage
Analyse
Status
In Progress
Start Date
08-Jan-2025
Planning Date
21-Feb-2025
Delivery Date
31-Oct-2025
Close Date
30-Nov-2025
Overall Priority
Normal

Documentation