Report for September 2025

Report Date
September 2025

 

Achievements this month

 

  • review reports to emphasis risks - done 
  • undertake a cost of ownership analysis for options - done

 

Issues/Risks

  • none

 

Next Steps

  • prepare a draft one page options paper for Sponsor
  •   

Milestones

Deliver     31-Oct-2025
Close 30-Nov-2025

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Escalated to
Project Sponsor
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
RDS Infrastructure Review
Code
LUC079
Programme
Library & Collections - Digital Library BAU (LUCDL)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Rebecca Hirsch
Current Stage
Analyse
Status
In Progress
Start Date
08-Jan-2025
Planning Date
21-Feb-2025
Delivery Date
31-Oct-2025
Close Date
30-Nov-2025
Overall Priority
Normal