Report for September 2025

Report Date
September 2025

Achievements in last period

  • Ongoing development work

Issues / Risks

  • None

Next steps

  • Complete Release 2 Development
  • Soft Launch platform
  • Complete Comms Plan
  • Complete Product Management Approach
  • Complete Accessibilty Testing Plan
  • Project Closure

Remaining Milestones

Stage Milestone Due Date Previous Date Complete  
Execute Release 2 Development complete 02-Oct-2025 19-Sep-2025 No

view

Execute UAT complete 02-Oct-2025 14-Sep-2025 No

view

Deliver Deployment Review 02-Oct-2025 11-Sep-2025 No

view

Deliver Platform soft launched 07-Oct-2025 30-Sep-2025 No

view

Close Project closure 31-Oct-2025 No date available No

view

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Digital Collections Platform Design
Code
LUC080
Programme
Library & Collections - Digital Library BAU (LUCDL)
Management Office
ISG PMO
Project Manager
Gavin Willshaw
Project Sponsor
Rebecca Hirsch
Current Stage
Initiate
Status
In Progress
Start Date
01-Feb-2025
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Oct-2025