Closure Report

Project Summary

This project was concerned with the design of the front end of the Digital Collections Platform (Archipelago), specifically the look and feel of the platform and how it meets the needs and requirements of its users. It culminated in the soft launch of University of Edinburgh Digital Collections (EDC) https://digital.collections.ed.ac.uk/

Stage Milestone Due Date Previous Date Complete  
Initiate Project Initiation complete 28-Feb-2025 No date available Yes

view

Execute Release 1 Requirements complete 31-Mar-2025 No date available Yes

view

Execute UX Approach agreed 31-Mar-2025 No date available Yes

view

Plan Project Brief submitted to Planning Review 18-Apr-2025 No date available Yes

view

Execute Release 1 Development complete 13-Jun-2025 31-May-2025 Yes

view

Execute Release 1 Usability Testing complete 18-Jul-2025 No date available Yes

view

Execute Release 2 Requirements complete 31-Jul-2025 No date available Yes

view

Execute Release 2 Development complete 02-Oct-2025 19-Sep-2025 Yes

view

Execute UAT complete 02-Oct-2025 14-Sep-2025 Yes

view

Deliver Deployment Review 02-Oct-2025 11-Sep-2025 Yes

view

Deliver Platform soft launched 07-Oct-2025 30-Sep-2025 Yes

view

Close Project closure 30-Nov-2025 31-Oct-2025 No (Planned)

view

Objectives and Deliverables Achieved

No

Objectives / Deliverables

MOSCOW

RESPONSIBILTY

Achieved?

O1

To soft launch the new Digital Collections Platform

 

 

 

D1

Digital Collections Platform website

Must

Project Manager

Yes

O2

To ensure the new platform meets the main usability requirements of its core user groups

 

 

 

D2

UX Approach document

Must

Project Manager

Yes

D3

Release 1 (R1) Requirements document

Must

Technical Lead

Yes

D4

R1 technical development

Must

Technical Lead

Yes

D5

Usability Testing plan

Must

Project Manager

Yes

D6

R1 Usability Testing script

Must

Project Manager

Yes

D7

R1 Usability testing schedule

Must

Project Manager

Yes

D8

R1 Usability testing feedback document

Must

Project Manager

Yes

D9

Release 2 (R2) Requirements document

Must

Technical Lead

Yes

D10

R2 technical development

Must

Technical Lead

Yes

D11

UAT document

Must

Technical Lead

Yes

O3

To propose an approach for continuous iterative development and improvement of the the platform, as well as ongoing user engagement

 

 

 

D12

Proposal for ongoing iterative development and  UX activity

Must

Project Manager

Yes

O4

To produce a plan for accessibility testing post project

 

 

 

D13

Plan for accessibility testing post soft launch

Must

Technical Lead

Yes

O5

To implement an appropriate project management approach

 

 

 

D14

Project Homepage has been created on ISG's Projects Website

Must

Project Manager

Yes

D15

Channel on MS Teams

Must

Project Manager

Yes

D16

Teams folder structure

Must

Project Manager

Yes

D17

WBS

Must

Project Manager

Yes

D18

Project Brief

Must

Project Manager

Yes

D19

Closure Report

Must

Project Manager

Yes (this document)

Analysis of Resource Usage:

Not Applicable

Explanation for Variance

Not Applicable

Outcome

The new Digital Collections Platform was successfully soft launched in October 2025, with a plan in place for ongoing iterative development and media uploads

Benefit

Recipient(s)

Timeline for Realisation

Owner

Achieved?

Improved user experience for accessing digital collections

Users

Project end

Rebecca Hirsch

Yes

Defined roles and responsibilities for the management and access of digital collections

Digital Library team

Project end

Rebecca Hirsch

Yes

Platform feels part of the wider Library digital estate, through consistent adherence to library visual identity guidance

 

Digital Library team

Project end

Rebecca Hirsch

Yes

Digital Collections Platform adheres to web accessibility guidelines

Digital Library team

Project end

Rebecca Hirsch

Not yet, planned

Key Learning Points

Ref Date Title Impact Theme Stage  
1 13-Nov-2025 Too much usability testing Should implement as good practice Resourcing Execute

view

2 13-Nov-2025 Not enough time to complete all development work Should implement as good practice Technology Execute

view

3 13-Nov-2025 Unneccessary use of both MS Planner and JIRA Should implement as good practice Technology Execute

view

4 13-Nov-2025 Project ran well despite lack of PMO resource Should implement as good practice Management of a Project Execute

view

5 13-Nov-2025 Underestimated time commitment of project team Should implement as good practice Resourcing Execute

view

6 13-Nov-2025 Accessibility Testing not complete at soft launch Should implement as good practice Technology Deliver

view

7 13-Nov-2025 Over reliance on one developer, whose time was split across two projects Was detrimental Resourcing Execute

view

8 13-Nov-2025 Did not include Comms Plan in Project Brief Should implement as good practice Management of a Project Execute

view

Outstanding Issues

There are some oustanding issues on JIRA, which will be migrated to the Digital Collectons Project product team and included as BAU work

Project Info

Project
Digital Collections Platform Design
Code
LUC080
Programme
Library & Collections - Digital Library BAU (LUCDL)
Management Office
ISG PMO
Project Manager
Gavin Willshaw
Project Sponsor
Rebecca Hirsch
Current Stage
Initiate
Status
In Progress
Start Date
01-Feb-2025
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Oct-2025
Overall Priority
Normal

Documentation

Close