- Report Date
- October 2025
Achievements in last period
- Completed Release 2 Development
- Soft Launched platform (https://digital.collections.ed.ac.uk/)
- Completed Comms Plan
- Completed Product Management Approach
- Completed Accessibilty Testing Plan
Issues / Risks
- Slight delay in Closure Report means project will close in November rather than October 2025
Next steps
Remaining Milestones
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days