The lecture recording implementation is split into workstreams.  This workstream will deal with the implementation of software.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
October 2017 BLUE 0.0 days 0.0 days 0.0

Project Info

Project
Lecture Recording (Software)
Code
MLE003-2
Programme
ISG - Lecture Recording (MLE)
Management Office
ISG PMO
Project Manager
Colin Forrest
Project Sponsor
Anne-Marie Scott
Current Stage
Close
Status
Closed
Start Date
06-Mar-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Nov-2017

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.