Project Status Reports

Title Report Date Time Cost Scope Overall Change
Feb 2019 February 2019 GREEN GREEN GREEN GREEN No Change
Jan 2019 January 2019 GREEN GREEN GREEN GREEN No Change
Dec 2018 December 2018 GREEN GREEN GREEN GREEN No Change
Nov 2018 November 2018 GREEN GREEN GREEN GREEN No Change
Oct 2018 October 2018 GREEN GREEN GREEN GREEN
Sep 2018 September 2018 GREEN GREEN GREEN GREEN
Aug 2018 August 2018 GREEN GREEN GREEN GREEN
Jun 2018 June 2018 GREEN GREEN GREEN GREEN
May 2018 May 2018 GREEN GREEN GREEN GREEN
April 2018 April 2018 GREEN GREEN GREEN GREEN
March 2018 March 2018 GREEN GREEN GREEN GREEN
February 2018 February 2018 GREEN GREEN GREEN GREEN
January 2018 January 2018 GREEN GREEN GREEN GREEN
December 2017 December 2017 GREEN GREEN GREEN GREEN
November 2017 November 2017 GREEN GREEN GREEN GREEN
September 2017 September 2017 GREEN GREEN GREEN GREEN
eScript VLE Migration - Project Status July 2017 July 2017 GREEN GREEN GREEN GREEN
eScript VLE Migration - Project Status June 2017 June 2017 GREEN GREEN GREEN GREEN
eScript VLE Migration - Project Status May 2017 May 2017 GREEN GREEN GREEN GREEN
eScript VLE Migration - Project Status April 2017 April 2017 GREEN GREEN GREEN GREEN
eScript VLE Migration - Project Status March 2017 March 2017 GREEN GREEN GREEN GREEN
eScript VLE Migration - Project Status February 2017 February 2017 GREEN GREEN GREEN GREEN
eScript VLE Migration - Project Status January 2017 January 2017 GREEN GREEN GREEN GREEN
Monthly RAG Status October 2016 GREEN GREEN GREEN GREEN