Report for February 2020
- Report Date
- February 2020
Achievements in Last Period
- GPFS Upgrade Successfully Completed
- GPFS Training Completed
- OpenStack Training - struggling to find dates - possible solution is to have a two "At Risk" period on next upgrade
- Prep work for Mini-Cluster Implementation
- Prep work for Go-CAB Paperwork
Issues and Risks
Open issues currently impacting on the project timeline, budget or scope:
- N/A
Any current or imminent risks that need to be managed:
- Project Delay - Due to Resource availability due to BAU and other Project work
- Project Delay - Due to a New Infrastructure Cluster formation not being understood by Management
- Project Delay - Due to Magt Go-CAB Approval
Next Steps
- Confirm Samba Clustering implementation
- IS Alert and Go-Cab for Samba Clustering Implementation
- Arrange OpenStack Training
- Conduct OpenStack Training
Future Milestones
(Milestones still in to show progress to date as Planning only just completed)
Milestone |
Date of Milestone |
9. Implement the recommended Samba Clustering |
Jun/Jul 19 Jan 20 Mar 20 |
10. Transition Users to the new DataStore Infrastructure Configuration |
Jun/Jul 19 Jan 20 Mar 20 |
11. Upgrade the DataStore GPFS Software |
28 Jun 19 5/6 Dec 19 10/11 Feb 20 |
12. GPFS Training (basic, advanced and Remote) Basic and Advanced Complete |
Feb/Jun/Dec 12-14 Feb |
19. Provide OpenStack Training for the RSS Systems Team |
May TBC? |
22. Delivery Complete |
28 Jun 19 19 Jul 19 31 Jan 20 27 Mar 20 |
23. Acceptance |
26 Jul 19 20 Feb 20 27 Mar 20 |
24. Closure |
20 Jul 19 26 Jul 19 21 Feb 20 10 Apr 20 |
25. Closure Project |
28 Feb 20 10 Apr 20 |
GUIDE TO RAG STATUS : project_planning_-_guide_to_rag_status.docx
Project Sponsor Commentary / Approval
- Approved
- Approved budget
- 178.0 days
- Activity this month
- 1.5 days
- Activity this year
- 23.8 days
- Activity to date
- 65.1 days
- Estimate to complete current year
- 112.9 days
- Estimate to complete future years
- 0.0 days