Report for February 2018
- Report Date
- February 2018
Report by Morna Findlay for February 2018
Achievements this Period
- Upgrade of TRN environment completed and signed off
- StuTalk update completed in TEST
- UAT of TEST environment completed
- Acceptance Signoff achieved
- Signoff from emergency CAB achieved
- LIVE upgrade achieved with minimal impact to users
Issues
- the budget for the project is likely to be reduced this month, if no showstopper issues are uncovered in TEST
- risk that planned industrial action may impact planned upgrade dates.
Next Steps
- re-estimate remaining tasks
- redesign refresh procedure
- deploy software upgrades
Milestones
| 29-Mar-2018 | Deployment Sign off LIVE Upgrade |
| 09-Apr-2018 | Refresh TEST |
| 16-Apr-2018 | Clone DUST from LIVE |
| 03-May-2018 | Close |
- Approved budget
- 220.0 days
- Activity this month
- 53.0 days
- Activity this year
- 154.0 days
- Activity to date
- 154.0 days
- Estimate to complete current year
- 66.0 days
- Estimate to complete future years
- 0.0 days