Report for March2018

Report Date
March 2018

Report by Morna Findlay for March  2018

 

Achievements this Period

 

  • Software updates applied to LIVE
  • Design of new refresh process under way
  • TRN fix applied

Issues 

  • the budget for the project is likely to be reduced this month, if no showstopper issues are uncovered in TEST
  • DSOR not signed off as some issues are being pursued in LIVE with Tribal

Next Steps

 

  • sign off LIVE deployment
  • re-estimate remaining tasks
  • refresh TEST
  • clone DUSt from TEST

 

Milestones

 

29-Mar-2018 Deployment Sign off LIVE Upgrade    
09-Apr-2018 Refresh TEST
16-Apr-2018 Clone DUST from LIVE
03-May-2018 Close

 

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
220.0 days
Activity this month
53.0 days
Activity this year
154.0 days
Activity to date
154.0 days
Estimate to complete current year
66.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SITS Double Upgrade
Code
SAC061
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Brandi Headon
Current Stage
Close
Status
Closed
Start Date
02-Oct-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
1
Overall Priority
Normal
Category
Compliance