Report for April 2018

Report Date
April 2018

Report by Morna Findlay for April   2018

 

Achievements this Period

  • new refresh process ( refresh followed by deletion of sensitive data) approved
  • TEST refreshed from LIVE
  • Software updates re-applied to TEST
  • DUST cloned from TEST
  • Two post-deployment LIVE JIRA issues resolved 

Issues 

  • One JIRA remaining - resolution expected w/c 30 April
  • Closure delayed due to delay to final signoff of last JIRA and subsequent annual leave of project manager 

Next Steps

 

  • resolve remaining JIRA
  • Proceed to closure

 

Milestones

 

18-May-2018 Close

 

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
RAG Commentary
Change: Closure milestone delayed to allow time for closure process after resolution of final JIRA.
Change Status
Activity
Approved budget
220.0 days
Activity this month
30.0 days
Activity this year
198.0 days
Activity to date
198.0 days
Estimate to complete current year
2.0 days
Estimate to complete future years
0.0 days

Project Info

Project
SITS Double Upgrade
Code
SAC061
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Brandi Headon
Current Stage
Close
Status
Closed
Start Date
02-Oct-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Programme Priority
1
Overall Priority
Normal
Category
Compliance