Report for April 2018
- Report Date
- April 2018
Report by Morna Findlay for April 2018
Achievements this Period
- new refresh process ( refresh followed by deletion of sensitive data) approved
- TEST refreshed from LIVE
- Software updates re-applied to TEST
- DUST cloned from TEST
- Two post-deployment LIVE JIRA issues resolved
Issues
- One JIRA remaining - resolution expected w/c 30 April
- Closure delayed due to delay to final signoff of last JIRA and subsequent annual leave of project manager
Next Steps
- resolve remaining JIRA
- Proceed to closure
Milestones
| 18-May-2018 | Close |
- Approved budget
- 220.0 days
- Activity this month
- 30.0 days
- Activity this year
- 198.0 days
- Activity to date
- 198.0 days
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 0.0 days