Assessment and Progression 3 - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2019 GREEN 0.0 days 0.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 21 August 2017
Planning Date
Friday, 26 January 2018
Delivery Date
Tuesday, 31 July 2018
Close Date
Friday, 30 August 2019
Project information
Project Code
SAC063
Programme
Student Systems Partnership SSP
Session
19/20
18/19
17/18
Organisational Unit
Student Services
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Discretionary
Project Classification
Grow
Overall Priority
Normal
Student Impact
Project deliverables will be used by staff on behalf of students