Project Report for February 2025
- Report Date
- February 2025
Achievements this period
- O2 - User Acceptance Testing complete and signed off in TRN environment
- O3 - Further technical legacy work has been absorbed into this project for the purposes of reporting
Issues
- (NEW) O2 - Deployment into LIVE environment on Thursday 27 February had to be abandoned due to unforeseen system issues. A new go-LIVE date is therefore necessary (RESOLVED)
Next Steps
- O2 - Packages to be deployed into LIVE environment
- O2 - Packages to be run by Operations in LIVE environment
- O2 - Deployment sign off review
- O1 - STU updates to be switched off
- O3 - Further technical legacy work to be completed
- Project closure
Key Milestones
| Stage | Milestone | Due Date | Previous Date | Complete |
|---|---|---|---|---|
| Build | O1 STU updates switched off | 28-Feb-2025 | 31-Jan-2025 | No |
| Deliver | Delivery sign-off review | 14-Mar-2025 | No date available | No |
| Deliver | O3 - Additional Technical Legacy work complete | 21-Mar-2025 | No date available | No |
| Close | Project Closure (MAJOR MILESTONE) | 28-Mar-2025 | 25-Apr-2025 | No |
- Approved budget
- 265.0 days
- Activity this month
- 20.5 days
- Activity this year
- 160.3 days
- Activity to date
- 263.2 days
- Estimate to complete current year
- 9.8 days
- Estimate to complete future years
- 0.0 days