Project Report for April 2025
- Report Date
- April 2025
Achievements this period
- O3 - Most VUE upgrades complete
- Budget increase agreed at Apps Review
Issues
- (NEW) (RESOLVED) Current applicants' data/documents accidentally deleted as part of O2
- (NEW) (ONGOING) Sync to STU tables to be switched off once confirmed able to do so by Enterprise Architecture as they are currently using them
- (NEW) (ONGOING) Potential budget overspend due to the above. Budget is 212d, actual effort this year 211 days and may increase due to additional effort/time needed from DevTech and Production.
Next Steps
- O2 - Packages to be rerun by Operations in LIVE environment
- O2 - Deployment sign off review
- O3 - Direct Admissions and UG Admissions VUE upgrades to be completed
- Project closure
Key Milestones
| Stage | Milestone | Due Date | Previous Date | Complete |
|---|---|---|---|---|
| Accept | O2 - deletions run for 1st year as BAU | 18-Apr-2025 | No date available | No |
| Deliver | Delivery sign-off review | 30-Apr-2025 | 14-Mar-2025 | No |
| Deliver | O3 - Additional Technical Legacy work complete | 09-May-2025 | 21-Mar-2025 | No |
| Close | Project Closure (MAJOR MILESTONE) | 16-May-2025 | 28-Mar-2025 | No |
- Approved budget
- 312.0 days
- Activity this month
- 22.7 days
- Activity this year
- 208.8 days
- Activity to date
- 311.7 days
- Estimate to complete current year
- 2.6 days
- Estimate to complete future years
- 0.0 days
