Project Report for May 2025
- Report Date
- May 2025
Achievements this period
- O3 - Most VUE upgrades complete
- Regrouping session with wider project team took place, next steps established. Further devepopment, testing and releases required for O2.
Issues
- (EXISTING) (ONGOING) Sync to STU tables to be switched off once confirmed able to do so by Enterprise Architecture as they are currently using them
- (EXISTING) (ONGOING) Budget increase required. Currently estimating required effort. Milestones to be updated thereafter.
Next Steps
- Project milestones to be updated
- O2 - Budget increase to be submitted
- O2 - Deployment sign off review
Key Milestones
| Stage | Milestone | Due Date | Previous Date | Complete |
|---|---|---|---|---|
| Accept | O2 - deletions run for 1st year as BAU | 18-Apr-2025 | No date available | No |
| Deliver | Delivery sign-off review | 30-Apr-2025 | 14-Mar-2025 | No |
| Deliver | O3 - Additional Technical Legacy work complete | 09-May-2025 | 21-Mar-2025 | No |
| Close | Project Closure (MAJOR MILESTONE) | 16-May-2025 | 28-Mar-2025 | No |
- Approved budget
- 312.0 days
- Activity this month
- 8.1 days
- Activity this year
- 216.9 days
- Activity to date
- 319.8 days
- Estimate to complete current year
- 16.0 days
- Estimate to complete future years
- 0.2 days