- Report Date
- June 2025
Achievements this period
- O3 - Most VUE upgrades complete
- Updated/fixed deletion code has been deployed to DUST environment for review
Issues
- (EXISTING) (ONGOING) Sync to STU tables to be switched off once confirmed able to do so by Enterprise Architecture as they are currently using them
- (EXISTING) (ONGOING) Budget increase required. Currently estimating required effort. Milestones to be updated thereafter.
Next Steps
- Project milestones to be updated
- O2 - Budget increase to be submitted
- O2 - Updated/fixed deletion code to be signed off in DUST environment
- O2 - Updated/fixed deletion code to be deployed to and signed off in other lower environments
- O2 - Updated/fixed deletion code to be deployed to and signed off in LIVE environment
- Project closure
- Approved budget
- 312.0 days
- Activity this month
- 6.7 days
- Activity this year
- 223.6 days
- Activity to date
- 326.5 days
- Estimate to complete current year
- 8.2 days
- Estimate to complete future years
- 0.7 days