Project Report for April 2024
- Report Date
- April 2024
Achievements this period
- Project initiated
- Business analysis underway
- Necessary resource requested
Issues
- Availability of one of the Business Analysts - planning adjusted to account for this. See Risk 5
Next Steps
- Project brief to be signed off
- Next stage of business analysis - see Work/Task Breakdown
Milestones
| Stage | Milestone | Due Date | Previous Date | Complete |
|---|---|---|---|---|
| Plan | Project Brief Completion (MAJOR MILESTONE) | 01-May-2024 | No date available | No |
| Deliver | Delivery of Project Outcomes (MAJOR MILESTONE) | 23-Sep-2024 | No date available | No |
| Close | Project Closure (MAJOR MILESTONE) | 08-Nov-2024 | No date available | No |
- Approved budget
- 120.0 days
- Activity this month
- 19.8 days
- Activity this year
- 22.2 days
- Activity to date
- 22.2 days
- Estimate to complete current year
- 47.1 days
- Estimate to complete future years
- 43.3 days